Tesla Megapack 3: Green Turtle Belgium 700MW/2.8GWh Sep 2026

Tesla Megapack 3: Green Turtle Belgium 700MW/2.8GWh Sep 2026

  • News
  • Rocks on Galaxy
  • Tesla
  • 29 Sep, 2026
  • 0

Tesla’s biggest Belgian battery bet is now dirt and concrete. On September 17, 2026, GIGA Storage announced that construction has started on Green Turtle in Dilsen-Stokkem—640 Tesla Megapack 3 units for 700 MW of power and 2,800 MWh of storage.

Who builds what

Tesla is the EPC partner: engineering, Megapack 3 supply, construction, commissioning, and long-term maintenance. Belgian contractor STADSBADER CONTRACTORS handles civil works for Tesla (earthworks and concrete; STADSBADER separately cited ~45,000 m³ of soil and 7,350 m³ of concrete). Preparatory earthworks began mid-August; official construction kickoff was September 17.

  • Site: former zinc factory, Rotem industrial estate
  • Grid: direct link to Elia’s new Rotem high-voltage substation beside the 380 kV Van Eyck–Gramme line
  • Chemistry: cobalt-free LFP (lithium iron phosphate), per GIGA Storage
  • COD target: end of March 2028
  • Peak claim: electricity equivalent to daily use of ~385,000 households

Scale and caveats

VRT coverage pegged investment around €700 million. GIGA Storage projects ~665,794 tonnes of CO₂ avoided per year once operational (developer claim—treat as modelled, not audited). Landscaping includes 26,650 m² of native planting and ecological protocols for toad migration during works.

This is a utility BESS story—distinct from Tesla Semi Nevada volume, Optimus manufacturing, Robotaxi/Cybercab fleets, and FSD Belgium testing covered elsewhere.

Why Megapack 3 matters here

Four-hour duration at 700 MW / 2.8 GWh is grid-balancing hardware, not a pilot row. Pairing Tesla EPC with a new Elia substation collapses the usual “batteries waiting on interconnection” delay that kills European storage timelines. Watch transformer delivery and COD slippage into 2028 more than ribbon-cutting quotes.

Rocks take

Strong, multi-source construction start with concrete Megapack 3 counts and a dated COD. Source: GIGA Storage.

FAQ

When does Green Turtle go live? Planned end of March 2028 per GIGA Storage.

Is this FSD-related? No—utility energy storage only.